ML (UK) DREDGING were very proud to have been awarded the 2019 dredging campaign at Brighton Marina.
The contract involved the removal of 19,000 cubic meters of material from the marina to gain deeper berths and wider deeper access within the entrance channel.
Works were completed in around three weeks. A commendation to our fully qualified, experienced crews for their haste, efficiency and professionalism during this dredge.
Whilst at Brighton the Witton was entrusted with the relocation of the channel entrance markers that had drifted out of their position. The Liebherr 964 has a reach of over 15m and more then enough power. Using GPS we were able to place these back in position making the entrance safe to navigate.

A huge thank you to all the staff for assisting us in the smooth running of this dredging campaign and we look forward to returning next year!.