Dredging Bray marina Windsor

ML DREDGING have been invited to Bray Marina to carry out some redundant pontoon removal and shore based maintenance dredging.  This idealic marina in Windsor has to be one of the most peaceful tranquil marinas on the Thames and we are delighted to be entrusted with the following excavation tasks.

Using our 30 tonne long reach excavator we created a bunded pit on land.  The area created was to cater for 300 cubic metres of material to be deposited.

Our long reach excavator using all of the 18m reach she has to offer then dredged from the marina to the required depth and deposited the material into the bunded area we created.

Dredging Bray Marina

Once we had taken care of the dredging it was down to our plough boat ”Beaver” rigged up with a 2 metre wide plough frame which gets lowered to the required depth and pulled along the marina bed to ensure we have reached our dredge targets.

All operations were carried out and completed within two weeks and we thank the staff at Bray marina for their support throughout the dredge.

If you are interested in berthing your boat at Bray marina check out the link below!

http://www.mdlmarinas.co.uk/mdl-bray-marina

News

Dredging Brighton Marina
55,000m3 dredge at Brighton Marina
55,000m3 dredge at Brighton Marina

  ML (UK) DREDGING LTD have been awarded the contract for the removal of 55,000m3 of naturally deposited sand and […]

Read full story
Back at it in Gosport Marina.
Back at it in Gosport Marina.

  ML Dredging are back at Gosport Marina! ML have yet again been awarded the dredging contract for Gosport Marinas […]

Read full story
ML Slipways
ML Slipways

  ML have recently taken over a commercial boatyard, slipway and general storage space in the heart of Hythe! With […]

Read full story
View All
Back to top